Exterior wall framing and setting of precast wall panels is being done at the Radisson Paper Valley Hotel.
Concrete floors have been poured around the escalator/stair landing area, and steel stairs were installed at the Radisson Paper Valley Hotel.
Precast panels are being set at the Radisson Paper Valley Hotel. At the Exhibition Center, steel stairs are being prepped for installation from
Escalators have been set at the Radisson Paper Valley Hotel.
Structural steel placement has begun at the Radisson Paper Valley Hotel.
Backfilling of foundations for the walkway bridge at the Radisson Paper Valley Hotel is complete, and the area is ready for structural steel and
Foundation work to support the structural steel for the walkway bridge at the Radisson Paper Valley Hotel is nearly complete.
Foundation work to support the structural steel for the walkway bridge continues at the Radisson Paper Valley Hotel.
Foundation work continues at the Radisson Paper Valley Hotel, and footings were poured for the future storefront/entrance along West Lawrence Street.
The masonry crew completed the new elevator shaft at the Radisson Paper Valley Hotel this week; helical piles continue to be installed.